Water & Sewer Line Replacement Project

This page will provide updates and information regarding the City wide Water & Sewer Line Replacement Project.

Questions or Concerns? Please contact the City directly at 463-3511, Monday through Friday, 8am to 5 pm


Q&D Construction has mobilized in Yerington for the Water and Sewer Project.

At this time you may see the potholing throughout town in preparation for this project. This will occur well ahead of the main construction effort and may ebb and flow depending on the crew’s daily schedule. Please contact City Hall with any questions.


Construction Schedule

APRIL 17 – APRIL 23

For water connections, Q & D Construction will be working on Whitacre Avenue, Whitacre alley, Grove, and West Street. Water main testing will occur all next week.


For sewer connections, Q & D Construction will be working on Mountain View, Whitacre Avenue, and Whitacre alley.


Please see the below road closure map for next week, April 17th through April 23rd. 

For any questions, please contact City Hall at 463-3511