Q&D Construction has mobilized in Yerington for the Water and Sewer Project.

At this time you may see the potholing throughout town in preparation for this project. This will occur well ahead of the main construction effort and may ebb and flow depending on the crew’s daily schedule. Please contact City Hall with any questions.


Construction Schedule

JUNE 7th – JUNE 11th

Q & D Construction will be working on water connections on Whitacre Avenue and Whitacre Block.

Q & D Construction will be working on sewer connections on Whitacre Avenue. The intersection of Goldfield Avenue and Main Street will begin work on June 8th and will be completed by June 11th.

Lateral connections will be worked on all week for both water and sewer. 

Grade for paving will begin on June 14th. Paving will also begin on June 14th on Mountain View, Whitacre Avenue, Memory Lane, and Van Ness Street.

South Lyon Medical Center tie overs will be completed on June 15th.

Video staking in the Colony for water connections will begin on June 14th. Water connections and construction will start on June 22nd.

A road closure map is provided below.